Construction Updates
Progress as of August 2025
- Submitted plans to City: Jan 5th 2024
- Plans approved by City
- Building Permits received
- Contract for Civil works signed
- Civil Contract execution started - August 2025
Activities 2025 - Phase 1
- Remove Trees and obstructions
- Remove Barn and House on property
- Prepare Retention Pond
- Complete plumbing (rainwater pipes, manholes)
- Level and prepare parking lot in front of the existing building
- Build Curbs and lay Asphalt (2") and make the lot useable